MSK Relocation at St Marks Hospital
Tags
- Major projects
Overview
The relocation of Jubilee Ward to Charles Ward is a strategic project supported by key stakeholders, including the Executive, Frimley ICB, NHSPS, and local councillors. Due to risks at Jubilee’s current location and the need to complete capital works across two financial years, services on Charles Ward must vacate by 31st October 2025. This enables refurbishment to begin in November 2025, ensuring the move is completed by Summer 2026.
Project Objectives
- Vacate Charles Ward by 31st October 2025.
- Relocate MSK services to Block 16 and Talking Therapies to Foundation House.
- Complete all works between 21st October 2025 and 26th November 2025.
- Deliver a safe, compliant clinical environment meeting IPC, water safety, and fire safety standards.
Key Features
- Compliant heating and cooling across patient areas.
- New DDA-compliant patient toilet and entrance.
- Dedicated cleaning and utility spaces.
- Uplift building to current compliance standards.
- Adapted IPS design solutions for infection control.
Design Approach
- Addressed space limitations holistically to maximize functionality.
- Implemented innovative plumbing solutions for efficient flow.
- Ensured compliance with infection control, water safety, and fire safety requirements.
Funding & Support
- MSK relocation to Block 16: £170k for modernization, IPC upgrades, acoustic treatment, IT installation, and accessibility improvements.
- Talking Therapies relocation to Foundation House: £15k for acoustic management and minor works.